A critical hybrid workload must survive the loss of an entire Direct Connect location. Which design changes provide the most appropriate resilience? Select 2 answers.

Published
  1. Increase the BGP keepalive timer so routes remain after a facility failure.
  2. Use two VLANs on one customer router without a second location.
  3. Create two virtual interfaces on the same physical connection.
  4. Use independent customer equipment and test the intended failover routing.
  5. Provision connections through separate Direct Connect locations.

Comments — 0