A critical hybrid workload must survive the loss of an entire Direct Connect location. Which design changes provide the most appropriate resilience? Select 2 answers.
Published
- Increase the BGP keepalive timer so routes remain after a facility failure.
- Use two VLANs on one customer router without a second location.
- Create two virtual interfaces on the same physical connection.
- Use independent customer equipment and test the intended failover routing.
- Provision connections through separate Direct Connect locations.