A company must move 300 virtual machines to AWS with minimal application changes under a short data-center exit deadline. Which migration approach should it evaluate first?
Published
- Move only static files and leave all required database dependencies behind without connectivity.
- Rehost suitable servers with AWS Transform MGN and test cutover groups.
- Export DNS records and assume application disks are migrated.
- Rewrite every application into microservices before moving any workload.