A disaster-recovery team wants to exercise a replicated application without interrupting the production source. Which operation is designed for a controlled recovery exercise?
Published
- Disable replication permanently
- Perform an unplanned production failover for every rehearsal
- Delete the production VM before testing
- A test failover into an isolated test network