A production pipeline misses its service target and consumes more resources. Which evidence should operations correlate?

Published
  1. Task duration and failures, compute utilization, data volume, and cost-related usage
  2. Only the dashboard's color theme
  3. Only the number of notebooks
  4. Report success because some output rows exist