A team has many partially completed items and long waits between development and testing. Which process improvement best targets flow rather than merely starting more work?

Published
  1. Make work visible, limit work in progress, and address the testing bottleneck
  2. Hide blocked items from the board
  3. Start every backlog item simultaneously
  4. Measure productivity solely by typing speed