CedarHealth is moving a legacy clinical application with many undocumented database and network dependencies. Downtime tolerance is low. What should guide the migration sequence?
Published
- Measure success only by how many servers are copied.
- Select the newest service for every component without compatibility checks.
- Move all components simultaneously before documenting dependencies.
- Discover dependencies, rehearse representative migrations, and use phased cutovers with measured recovery plans.