External project access should expire automatically unless renewed through an authorized process. Which design most directly supports this?

Published
  1. A shorter DNS TTL
  2. Permanent assignments with no owner
  3. Time-bound access-package assignments with appropriate extension and review policies
  4. A VM shutdown schedule