A control test samples only the best-managed branch, while the risk covers fifty branches. What should the practitioner question?

Published
  1. Whether the branch's control owner is senior
  2. Whether a larger report would solve the bias
  3. Whether the sample supports conclusions about the full scope
  4. Whether all sampling is invalid