A project sponsor asks the risk practitioner to guarantee that no security loss will occur. What should the practitioner explain?
Published
- An approved assessment guarantees zero loss
- Insurance guarantees that every consequence is recoverable
- A low risk rating means monitoring can stop permanently
- Risk management supports informed decisions under uncertainty rather than eliminating every possible loss