A risk appetite statement is approved but unknown to project decision-makers. What is the most useful next step?

Published
  1. Assign every risk the same numerical score
  2. Rely on informal interpretation by each project
  3. Translate and communicate it through decision criteria, training, and escalation examples
  4. Archive the statement as sufficient proof of adoption