A risk is accepted because further mitigation is disproportionate. A mandatory contractual control remains unmet. What should be clarified?
Published
- That low expected loss cancels every contract term
- Whether the obligation can lawfully and contractually be changed; internal acceptance alone does not waive it
- That all contractual duties are technical suggestions
- That the control operator can waive the contract privately