A risk owner chooses a control that reduces likelihood but does not change impact if the event occurs. What should the report show?

Published
  1. Zero impact because likelihood decreased
  2. The distinct effect on likelihood and the remaining consequence
  3. A guaranteed event date
  4. A transfer of ownership to the installer