A risk report ranks every issue critical to secure more funding. What is the main consequence?

Published
  1. Every control becomes legally mandatory
  2. The enterprise risk appetite increases automatically
  3. Decision-makers lose reliable prioritization and may misallocate resources
  4. The report automatically becomes more accurate