A risk treatment is judged successful solely because it complied with the implementation schedule. What additional evidence is needed?

Published
  1. Demonstrated achievement of the intended control outcome and residual-risk target
  2. Only confirmation that the project manager was satisfied
  3. Only a count of project meetings
  4. Only a final supplier invoice