A risk treatment is judged successful solely because it complied with the implementation schedule. What additional evidence is needed?
Published
- Demonstrated achievement of the intended control outcome and residual-risk target
- Only confirmation that the project manager was satisfied
- Only a count of project meetings
- Only a final supplier invoice