A treatment depends on a third party completing work, but no dependency milestone is tracked. What should be added?
Published
- Only the supplier's annual revenue
- A note that all external work is outside risk management
- An accountable dependency owner, agreed dates, monitoring, and contingency
- A promise to assume completion until told otherwise