A treatment project is delayed six months while current exposure remains high. What should the practitioner do?

Published
  1. Keep reporting the planned target risk as current risk
  2. Remove the milestone to avoid overdue reporting
  3. Wait silently until the new completion date
  4. Report the delay's risk effect and evaluate interim measures and escalation