A treatment project is delayed six months while current exposure remains high. What should the practitioner do?
Published
- Keep reporting the planned target risk as current risk
- Remove the milestone to avoid overdue reporting
- Wait silently until the new completion date
- Report the delay's risk effect and evaluate interim measures and escalation