A project meets its technical requirements but lacks evidence of business-user acceptance before release. What is the key control gap?

Published
  1. The business has not demonstrated that the system meets its operational requirements
  2. The development team did not choose a distinctive application name
  3. Unit testing must never occur before user acceptance
  4. The project must be cancelled regardless of the missing evidence

Comments — 0