A project meets its technical requirements but lacks evidence of business-user acceptance before release. What is the key control gap?
Published
- The business has not demonstrated that the system meets its operational requirements
- The development team did not choose a distinctive application name
- Unit testing must never occur before user acceptance
- The project must be cancelled regardless of the missing evidence