Six months after implementation, a project sponsor asks whether the system delivered its approved benefits. Which review addresses this?

Published
  1. A test limited to whether the application icon loads
  2. A repetition of procurement pricing without outcome assessment
  3. Only a review of the initial project kickoff agenda
  4. A post-implementation review against business objectives and control requirements