A migration rehearsal met database timing targets but omitted application validation. What is the best completion criterion?
Published
- Validate representative transactions, consistency, connectivity, and rollback readiness before production cutover.
- Declare success solely because the target listener accepts TCP.
- Skip compatibility checks because both products contain the Oracle name.
- Delete the source as soon as the first target table appears.