A DR team wants to reduce failures before an actual switchover. What should it do regularly with Full Stack DR?

Published
  1. Remove monitoring so transient recovery errors are not recorded.
  2. Replace the recovery plan with the application's marketing diagram.
  3. Assume the first generated plan remains correct after all application changes.
  4. Run plan prechecks and exercises, and fix detected dependency or permission issues.