A legacy application migration has a strict maintenance window and several undocumented database dependencies. What should happen before choosing the migration method?
Published
- Move the largest server first without dependency analysis.
- Assume every database supports identical migration tooling.
- Discover dependencies and data-change rates, then validate a cutover and rollback strategy.
- Delete the source backups to force teams to use the target.