A team wants to reduce disaster-recovery costs by shutting down recovery compute. Which constraint must be checked first?

Published
  1. Whether a stopped VM automatically meets every recovery objective.
  2. Whether provisioning time, capacity availability, and application startup still meet the required RTO.
  3. Whether DNS TTL alone defines the entire recovery duration.
  4. Whether backups can be removed because compute is stopped.