After a successful cutover, the team wants to decommission the source environment. What is the appropriate gate?

Published
  1. Keep untracked source credentials permanently active for convenience.
  2. Terminate the source immediately after the first successful login.
  3. Confirm acceptance, retained recovery evidence, backup obligations, and the agreed rollback-window closure.
  4. Delete all migration logs before stakeholders review the outcome.