A company has four servers that must cut over together. How should the Cloud Migrations project be organized?
Published
- Group the relevant migration assets around the coordinated cutover event and plan their dependencies.
- Move only the smallest server and assume the others follow automatically.
- Split them randomly so no plan contains related components.
- Delete the source servers before inventory completes.