A migration program needs an auditable acceptance decision. What should be defined during planning?

Published
  1. Only whether the new region name is shorter.
  2. A rule to skip testing when the transfer completes quickly.
  3. Functional, data, security, performance, and recovery criteria with named approvers.
  4. Only whether the target VM starts.