A migration program needs an auditable acceptance decision. What should be defined during planning?
Published
- Only whether the new region name is shorter.
- A rule to skip testing when the transfer completes quickly.
- Functional, data, security, performance, and recovery criteria with named approvers.
- Only whether the target VM starts.