A migration rehearsal exceeds the outage budget. What should the team do before production cutover?
Published
- Hide the rehearsal result and keep the original promise.
- Use measured phase timings to improve the plan or renegotiate the approved window and approach.
- Count only DNS update time as the total outage.
- Delete all checkpoints to make the plan shorter.