A target database is promoted and starts accepting new writes. What is required before reverting users to the original source?

Published
  1. Assume rollback can never require database work.
  2. Delete target transaction evidence before deciding.
  3. A defined data reconciliation or reverse-synchronization strategy and controlled rollback decision.
  4. Change DNS back and assume the source contains every target write.