A wave contains one failed asset and several healthy but dependent assets. What should guide the cutover decision?

Published
  1. Cut over every healthy VM independently regardless of dependencies.
  2. Count successful disk copies as the only acceptance criterion.
  3. Delete the failed source to force target adoption.
  4. The agreed dependency and acceptance gates for the complete application wave.