A workload is operational in OCI but costs far more than planned. What should the post-migration review assess?
Published
- Remove all backups unconditionally.
- Only the number of source servers originally discovered.
- Disable cost reporting so the plan appears correct.
- Actual utilization, shape choices, storage tiers, data movement, and attributable service consumption.