An online database migration reports a completed initial load but a nonzero change backlog. Is final cutover necessarily ready?
Published
- Yes; a new DNS name removes unapplied changes.
- Yes; the initial load guarantees every later transaction is already copied.
- No; online migration can never reduce downtime for any workload.
- No; the remaining changes and consistency conditions must satisfy the cutover criteria.