Before an approved change to a critical facility system, which TWO items should the team understand? Select TWO.
Published
- Only the technician's personal preference for the order of operations
- The expected operating state and dependencies affected by the change
- The authorized procedure, risk controls, and abort or recovery conditions
- A belief that redundant infrastructure makes procedures unnecessary