Before an approved change to a critical facility system, which TWO items should the team understand? Select TWO.

Published
  1. Only the technician's personal preference for the order of operations
  2. The expected operating state and dependencies affected by the change
  3. The authorized procedure, risk controls, and abort or recovery conditions
  4. A belief that redundant infrastructure makes procedures unnecessary