A building project has approved drawings and stable regulatory requirements. Rework late in construction is costly. Which approach is generally most suitable?

Published
  1. An approach chosen solely by team age
  2. A completely unplanned workflow
  3. Predictive planning with controlled changes
  4. Continuous scope replacement without approvals