A building project has approved drawings and stable regulatory requirements. Rework late in construction is costly. Which approach is generally most suitable?
Published
- An approach chosen solely by team age
- A completely unplanned workflow
- Predictive planning with controlled changes
- Continuous scope replacement without approvals