A coordinator is asked to report a task as complete even though its acceptance checks failed. What is the most appropriate action?
Published
- Report the actual status and follow the organization's escalation process
- Omit the task from the report until the next reporting cycle
- Change the checks after the task fails so it appears successful
- Report completion because the requester outranks the coordinator