A coordinator records that a regulatory review is expected to take ten business days, although the regulator has not confirmed this. How should this expectation initially be classified?

Published
  1. An assumption to validate and monitor
  2. A constraint that cannot change
  3. An approved change request
  4. A realized issue requiring immediate corrective action