A coordinator records that a regulatory review is expected to take ten business days, although the regulator has not confirmed this. How should this expectation initially be classified?
Published
- An assumption to validate and monitor
- A constraint that cannot change
- An approved change request
- A realized issue requiring immediate corrective action