A critical supplier has already missed today's delivery and assembly cannot start. Which record should capture the present problem, its owner, and resolution actions?

Published
  1. Product backlog as an optional feature
  2. Issue log
  3. Risk register only, with no current action owner
  4. Assumption log as an unverified forecast