A customer asks for an additional report after the scope baseline is approved. What should the coordinator do before directing implementation?

Published
  1. Reject every request made after baseline approval
  2. Add the report because customer requests automatically change scope
  3. Document the request and follow the defined change control process
  4. Ask a developer to implement it outside recorded work