A deliverable is technically complete but has not received formal customer acceptance. Which process concern remains?

Published
  1. Delete the acceptance requirement
  2. Record an unrelated risk as closed
  3. Validate the deliverable against acceptance criteria with the authorized customer
  4. Assume internal testing is automatically customer acceptance