A finish-to-start dependency links installation to configuration. Installation finishes later than planned. What should the scheduler evaluate?
Published
- Whether the sponsor has read the schedule
- The effect on the successor's start, float, and overall completion
- An automatic identical delay to every project activity
- Only the successor's task label