A hybrid project uses iterative software delivery inside a mandatory regulatory stage-gate process. Which statement is correct?
Published
- Using iterations automatically cancels regulatory obligations
- Every hybrid team must use the same fixed iteration length
- Adaptive delivery can operate within defined governance constraints
- A stage gate means no feedback may occur between gates