A Kanban team starts many items but finishes few. Which intervention most directly targets excessive work in progress?

Published
  1. Measure only individual utilization
  2. Introduce and respect work-in-progress limits, then help unblock existing items
  3. Make every item the highest priority
  4. Increase the number of items started each day