A manager is asked to report an unfinished deliverable as complete to protect a milestone bonus. What should the manager do?

Published
  1. Report actual status honestly and explain the gap
  2. Ask the team to change the original acceptance criteria secretly
  3. Omit the deliverable from all future reports
  4. Mark it complete because the bonus is contractual