A manager is asked to report an unfinished deliverable as complete to protect a milestone bonus. What should the manager do?
Published
- Report actual status honestly and explain the gap
- Ask the team to change the original acceptance criteria secretly
- Omit the deliverable from all future reports
- Mark it complete because the bonus is contractual