A manager shifts a noncritical activity within its available float to reduce a temporary resource peak without changing the finish date. What is this closest to?

Published
  1. Unrestricted resource leveling that must extend every project
  2. Scope expansion
  3. Resource smoothing
  4. Risk acceptance