A new stakeholder can approve a permit that the project needs, but the stakeholder is not in existing communication records. What should the coordinator do first?
Published
- Identify and assess the stakeholder, then update engagement planning
- Treat the stakeholder as a vendor and start procurement
- Send every project document without assessing information needs
- Wait until the permit is refused before making contact