A new stakeholder can approve a permit that the project needs, but the stakeholder is not in existing communication records. What should the coordinator do first?

Published
  1. Identify and assess the stakeholder, then update engagement planning
  2. Treat the stakeholder as a vendor and start procurement
  3. Send every project document without assessing information needs
  4. Wait until the permit is refused before making contact

Comments — 0