A predictive project baselines detailed requirements early. A stakeholder later requests a change. What should the analyst support?

Published
  1. Permanent refusal to discuss any change
  2. Silent implementation outside the baseline
  3. Impact analysis and the defined change process
  4. Automatic deletion of all previous requirements