A product team frequently discovers that customers do not want finished features. Which delivery practice best reduces this risk?

Published
  1. Increase batch size and defer all reviews
  2. Replace feedback with internal applause
  3. Release or demonstrate small usable increments to obtain early feedback
  4. Estimate every feature more precisely without user contact