A project may face a material shortage next quarter, but no shortage has occurred. Where should the team first record the uncertain event and its possible impact?

Published
  1. Risk register
  2. Lessons learned register as a completed response
  3. Issue log as a confirmed shortage
  4. Change log as an approved scope adjustment