A retailer temporarily assigns a team to open one new distribution center. After handover, warehouse employees will run it indefinitely. Which statement correctly distinguishes the work?
Published
- Running shipments is the project because it produces measurable results
- Both activities are projects because both consume resources
- Both activities are operations because the retailer already exists
- Opening the center is a project; running its daily shipments is operations