A team is asked to estimate a distant release while requirements remain uncertain. Which approach is most suitable?
Published
- Refuse to communicate any forecast under any circumstances
- Set the release date equal to the number of backlog items
- Guarantee one exact date from an untested guess
- Provide an assumption-based range and refine it as evidence develops