A team is asked to estimate a distant release while requirements remain uncertain. Which approach is most suitable?

Published
  1. Refuse to communicate any forecast under any circumstances
  2. Set the release date equal to the number of backlog items
  3. Guarantee one exact date from an untested guess
  4. Provide an assumption-based range and refine it as evidence develops