A team starts more work whenever someone becomes idle, but nearly finished items wait for review. What Kanban practice would most directly expose and reduce this problem?
Published
- Measure only how many items are started
- Hide review tasks from the board
- Raise the WIP limit indefinitely
- Limit work in progress and improve flow through the review bottleneck