A team starts more work whenever someone becomes idle, but nearly finished items wait for review. What Kanban practice would most directly expose and reduce this problem?

Published
  1. Measure only how many items are started
  2. Hide review tasks from the board
  3. Raise the WIP limit indefinitely
  4. Limit work in progress and improve flow through the review bottleneck