A team wants to compare the relative effort and uncertainty of backlog items without claiming exact completion dates. Which estimation technique fits?
Published
- Assigning each point a universal number of hours across all teams
- Counting features without considering their size
- Relative estimation using story points
- Using the sponsor's requested date as the estimate