A team wants to compare the relative effort and uncertainty of backlog items without claiming exact completion dates. Which estimation technique fits?

Published
  1. Assigning each point a universal number of hours across all teams
  2. Counting features without considering their size
  3. Relative estimation using story points
  4. Using the sponsor's requested date as the estimate